Barcelona are going to leave the Camp Nou again. This was already part of their plans to finish ongoing rebuilding works at their iconic ground, but now we know — following comments from vice-president Ferran Olive at Saturday’s annual general assembly — exactly what they expect to happen next.
Olive said Barca would finish this 2026-27 season at the
Camp Nou, but would then have to play away from the stadium for around half of
2027-28. He said the club hoped to come back in January 2028.
At that meeting, Barcelona also requested club members
approve another big loan — taking on €510million (£437m; $584m) in further
debt, €300m being earmarked for Camp Nou construction and €210m in further
operational borrowings — in order to complete the works. This was voted
through, meaning Barcelona’s total debts are now set to surge well past £2
billion and could hit €2.6bn in total, depending on repayment dates.
It takes the budget for the Espai Barca projevt which
encompasses the Camp Nou rebuild, to €1.8billion, or triple what the works were
costed at when it was first pitched in 2014. And even that sum won’t cover the
full project; president Joan Laporta told club members on Saturday the extra
€300m earmarked for the Camp Nou will not cover the building of the Palau
Blaugrana, a venue which will house the club’s non-football teams.
Olive said work on the roof would “start progressively as
soon as the team has played their last game of the season in May”. He said the club have already reached an
agreement with Barcelona’s city council to return to the Estadi Olimpic Lluis
Companys, the 1992 Olympics venue which has a capacity of around 45,000 for
football matches. Olive also said: “When we get back to the Camp Nou in January
2008, we expect to have a 95,000 seating capacity which will give us again this
full potential to get the financial side of the club working at its best.”
From this, it sounds like the ground will still not quite be
fully finished when Barca do go back. The total capacity of the new Camp Nou is
planned to reach 105,000, up from the previous official total of 99,354. That
was already the largest of any European football venue.
Now Barcelona expect to have the stadium finished and at
full capacity by the start of the 2028-2029 season. Last week, UEFA announced
it has chosen the Camp Nou as the 2029 Champions League final venue, set for
June 2 that year.
On the subject of delays, Olive added: “We expect all the
significant parts of the roof to be built by October or November 2027, but we
don’t want to be struggling with timings again.” Delays have already been costly for
Barcelona. Playing away from the Camp Nou for longer than they planned has
meant missing out on boosted revenues from the new ground, while the club also
said it spent €17million on “operating expenses” and €24m in “investment linked
to this stage”.
Barcelona’s Camp Nou rebuild costs have spiralled massively
from the original plans approved 12 years ago.
Earlier this month, financial forecasts were shared with Barcelona club
members. It pointed to new borrowing of around €300million for the rebuild and
an increased budget of €1.8billion. However,
on Saturday, members were instead asked to approve a higher total of new
borrowing — €510million. That amount spans both the Camp Nou works (€300m) and
further operational debt (€210m) taken on by Barca, with the latter secured
against future TV money.
The Espai project gobbles both cash and headlines, but
taking on yet more non-project debt is of concern. The Espai debt, large as it
is, is backed by the revenues which should eventually flow from a world-class
home and has been taken out in service of building such a ground; the other
debt was first taken out for liquidity purposes in 2021 and serves no such
long-term purpose.
Non-Espai debt comprised €597million of Barca’s total
€1.840bn in borrowings at the end of June 2026, so the extra €210m will take
those borrowings beyond €800m. Laporta
told members on Saturday the club were looking for solutions but assured them
it would not further raise a level of debt which already stands way out in
front as football’s largest.